【First-Class Constructor Project Management Practice Questions】019 Preparation of Construction Organization Design

2016-06-19View Original

Thread Content

29. According to the \"Code for Design of Construction Organization\" (GB/T50502-2009), the construction organization design shall be prepared under the organization of ( ). A. Technical supervisor of the construction unit B. Project manager of the construction unit C. Project technical supervisor of the construction unit D. Person in charge of the construction unit
Reply #22016-06-19
Then who is responsible for reviewing and approving it?
Reply #32016-06-19
【Standard Answer】B 【Expert Explanation】This question tests the preparation and approval of construction organization plans. The construction organization design shall be prepared under the supervision of the project leader, and can be prepared and approved in phases as needed.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.