【First-Class Constructor Project Management Practice Questions】026 Single-Code Time Interval

2016-06-19View Original

Thread Content

Regarding the time intervals in a single-code overlapping network plan, which statement is correct? ( ) A. The time interval is a specific time parameter associated with a certain task. B. There can be only one type of time interval constraint between adjacent tasks. C. The time interval is generally indicated above the arrow. D. The time interval is a special form of time gap
Reply #22016-06-19
【Standard Answer】C 【Expert Explanation】This question tests knowledge of single-code overlapping network plans. There are four types of time distances: STS, STF, FTF, and FTS. It is generally marked above the arrow.
Reply #32016-06-19
【Standard Answer】D 【Expert Explanation】This question tests the **quality supervision procedures for engineering projects. Project quality supervision archives are established on a per-unit-project basis.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.