Is it really necessary for cables to run in cable trays? Is direct pipe installation in compliance with the standards?

2016-08-10View Original

Thread Content

There are 8 instrument cables in the tank area; is it necessary to use cable trays? Can steel pipes be laid directly on the ground? How can one proceed in a way that is both compliant with regulations and reasonable? I hope an expert can help answer this. Thank you very much
Reply #22016-08-10
Or it can be elevated; it’s easy for water to get in if it’s at ground level
Reply #32016-08-10
This post was last edited by seiluobin on 2016-8-10 10:24. Of course, you can choose to install it directly within pipes or underground. As long as the site conditions permit, for loading cabinet rooms dedicated to tank areas where there are not many instrument points and no beam structures available for use as cable tray supports, burial is usually the preferred option. When burying such structures, it is necessary to ensure proper waterproofing; following the standard construction guidelines for burials will generally suffice.
Reply #42016-08-10
Piping is an option, but I personally think burying it makes future maintenance less convenient; there’s no need to use cable trays for small quantities of cables
Reply #52016-08-10
It can be run through a tube, but if the cable is too long, it’s difficult to pass it through the tube.
Reply #62016-08-11
How to move around in the tank area without pipes? Generally, pipe trenches are used for direct burial in tank areas.
Reply #72016-08-11
I’ve never heard that waterproofing is necessary; it’s not about renovating a toilet, but about laying pipes.
Reply #82016-08-11
I haven’t heard of any standards regarding the burial of cable protection pipes underground; could you provide such a standard? Tell me how deep to bury it, how to ensure waterproofing, and how to provide compressive strength.
Reply #92016-08-12
Everyone, please keep pinching~~~~:lol
Reply #102016-08-15
≥Minimum vertical burial distance: Below the permafrost layer in cold regions; there are minimum clearance requirements with respect to building foundations and electrical cables. There are also minimum distances required when running parallel to or intersecting with other pipes. When passing through roads, protective pipes must be used, and these pipes need to be waterproof. There is a minimum thickness requirement for the soil layer applied. I can’t remember exactly how many millimeters it is, but there definitely is such a requirement. Just because you haven’t heard of it doesn’t mean it doesn’t exist – have you learned something new?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.