Qualification assessment: Plate thickness of 40 mm; post-weld heat treatment: high-temperature tempering, with a holding time of 4 hours. The actual plate thickness used in construction is now 90 mm, and due to this thickness, the heat treatment time requires 8 hours. Can I use the assessment method mentioned above for this case? According to 6.1.4.2 in 47014-2011, the holding time of the test piece must be no less than 80% of the total holding time experienced by the welded part during manufacturing; therefore this requirement cannot be satisfied. This raises the question: what is then the purpose of the coverage range for the base material listed in Table 7 of 47014?
Reply #22016-12-20
The actual plate thickness has reached twice the evaluated thickness; it can no longer cover it
Reply #32016-12-26
It cannot be overlaid; both the plate thickness and the insulation time exceed the limits

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.