Lifting operations 3: Which lifting operations require the preparation of a lifting plan?

2023-07-10View Original

Thread Content

Lifting operations 3: Which lifting operations require the preparation of a lifting plan?
Reply #22023-07-11
1. Level-1 lifting operations. 2. Secondary lifting operations. 3. Lifting operations of objects with complex shapes, low stiffness, a large length-to-diameter ratio, and high precision or value.
Reply #32023-07-13
This post was last edited by Shutong on 2023-7-13 at 16:16. The above three scenarios are situations where the risks are relatively high and accidents are likely to occur during operations; thus, they require great attention during the course of operations. For Level 1 and Level 2 lifting operations, given the heavy weight of the loads being lifted, any accidents could have relatively serious consequences; therefore, a corresponding lifting plan must be developed. Although the mass of the object to be lifted is less than 40 tons, it has a complex shape, low stiffness, a high length-to-diameter ratio, and is delicate and valuable. Moreover, it involves level-3 lifting operations under special working conditions. Due to its delicacy and value, an accident could result in significant economic losses ; For lifting operations involving objects with complex shapes, low stiffness, a large length-to-diameter ratio, or under special operating conditions, the potential risks are relatively high. Preparing a lifting plan is essential to ensure the safe execution of such operations. The lifting plan should specify the procedures for lifting operations, conduct a comprehensive analysis of potential risks that may arise during such operations, and formulate corresponding safety control measures. At the same time, the plan should also specify the measures to address potential accidents that may occur during lifting operations, including injuries to personnel and damage to lifting equipment. Therefore, a lifting plan must be developed and strictly reviewed and approved in order to keep risks within acceptable levels.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.