On the tee problem in stress analysis software

2017-09-18View Original

Thread Content

230 degrees, 11 kg of steam; 50 branch pipes connected to the DN400 main pipe. Which type of tee should be used? Should I just use an unreinforced tee?
Reply #22017-09-18
If a hole is made directly without reinforcement, then that is…
Reply #32017-09-18
I have another question: in a fixed bracket, is the horizontal thrust on the sliding bracket essentially 0, with the forces canceling each other out?
Reply #42017-09-18
It is possible to order a DN400*50 tee directly, or to connect the pipes first and then make openings plus weld on the branch pipe connections
Reply #52017-09-18
Of course not... The horizontal force on the sliding bracket is frictional force; there is force as long as there is displacement.
Reply #62017-09-18
Unless specially customized, there are no such tees
Reply #72017-09-18
Regardless of which one, you use software for calculations; the stress increase varies for different types of tees, and it is sufficient to meet the requirements for the 1st and 2nd order stresses

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.