I would like to ask: for gas pipelines laid horizontally on top of utility tunnels, a vent pipe needs to be installed on the main gas pipeline. According to the standards, this vent pipe must be 4 meters higher than the highest point of the buildings within a 10-meter radius. As a result, the vertical section of the vent pipe ends up being quite tall. How are supports for such vertical vent pipes typically constructed? Also, I saw people using tension cables on site; is there a scientific name for such cables or any reference manuals available?
First of all, mine is an overpressure relief pipeline, not a flare, so flare supports are not considered; Additionally, before I led the vent pipe on the ductwork to the side of the columns in the surrounding factories and installed supports on those columns, I found that there was a section of horizontal pipe in the vent pipe, which caused considerable resistance; this approach wasn’t very suitable. Therefore, I would like to ask how the supports for the vent pipes on utility tunnels are constructed
First of all, mine is an overpressure relief pipeline, not a flare, so flare supports are not considered; Additionally, before I led the vent pipe on the ductwork to the side of the columns in the surrounding factories and installed supports on those columns, I found that there was a section of horizontal pipe in the vent pipe, which caused considerable resistance; this approach wasn’t very suitable. Therefore, I would like to ask how the supports for the vent pipes on utility tunnels are constructed
Is there a catalog for the pull cords? Or is it entirely dependent on structural engineering design?
Raise it directly on the steel structure, with the pipelines fixed vertically in the middle
Isn’t it a bit of a waste? There are tower-like structures in the surrounding area, so I need to increase the height by a lot
Is there tower-type equipment within ten meters around your pipeline trench? Could considering leading it horizontally for a distance be an option?
Is there tower-type equipment within ten meters around your pipeline trench? Could considering leading it horizontally for a distance be an option?