Why is a flange added after the position package is welded?

2021-01-20View Original

Thread Content

Why is a short-circuit flange installed on the clad steel plate after the position information is leaked, and what is the function of this short-circuit flange?
Reply #22021-01-20
Is the weld inside the short tube the original one?
Reply #32021-01-21
If nothing goes wrong, it’s another bizarre idea from a leader
Reply #42021-01-25
The original weld inside the short pipe had leakage; after sealing the leak, an additional weld was applied around the outside
Reply #52021-07-28
The short tube is used to guide the leaking medium during welding; otherwise, welding cannot be carried out. There are also those equipped with a valve; after welding, the valve is closed.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.