Piping pressure test

2018-07-13View Original

Thread Content

I happened to notice that the pressure required for testing containers was much lower than that required for testing pipes in the same system. The pressure needed for testing containers was 7.8 Mpa, while the pressure required for testing pipes reached 9.8 Mpa. The pressure requirements for pipes are thus much higher than those for equipment. Is this usually the case?
Reply #22018-07-13
The equipment factor is 1.25 times, and the pipeline factor is 1.5 times; there should be a temperature correction as well, so the difference isn’t that large
Reply #32018-07-13
When providing information to the equipment specialists and it is required that the equipment be pressure-tested along with the piping system, then the test pressure indicated on the nameplate will be the same as that of the piping system.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.