Settlement issues of pipeline crossings through fire dikes in tank farms

2019-05-29View Original

Thread Content

Hello, everyone in this forum. The pipes in our tank area are designed to pass through fire dikes, and the drawings require the use of sleeves, with asphalt hemp filler placed inside those sleeves. However, after prolonged operation, it was found that the pipes have settled significantly, with their bottoms almost touching the sleeves below. Does anyone have any good solutions for this issue? How do you deal with such problems?
Reply #22019-05-29
The pipeline settlement is severe; the geology in your area isn’t good. There’s not much that can be done after construction – you just have to adjust the supports
Reply #32019-07-16
Solve it completely, lay a solid foundation, address the settlement issue, and then provide support. It has to be done this way; it’s not easy

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.