Questions regarding the application for a visual kit

2020-12-22View Original

Thread Content

I’m seeking advice from experts: if both ends of a pipe are equipped with connections and there is no way to vent or drain the fluid, how can pressure testing of such a pipe be carried out? . The pipelines in the convection section of the cracking furnace run from one furnace port to the next; they are 8\" pipes with a length of around 20 meters. I really can’t think of a way to perform pressure testing – should they be removed and filled with water? ? And there are a total of 8 such tubes. . I put them all in one pressure testing bag
Reply #22020-12-25
Pressure testing should be carried out on each pipe individually; temporary blind flanges should be used. After testing, the pipes must be thoroughly purged. Welding to the equipment interfaces should be done in accordance with the Golden Port rules, and 100% non-destructive testing is required

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.