Does the Ej=1.0 requirement in the pipe description apply to the manufacturer or to the installer?

2022-02-11View Original

Thread Content

I would like to ask: in the description of pipe length in the grade table – “Pipe, API 5L PSL1 Gr.B, BE, ASME B36.10M, SAWH, Ej=1.0” – does the value Ej=1.0 apply to the manufacturer or to the contractor? Does it mean that all welds on the pipes must be inspected before they leave the factory, or that 100% inspection of the welds is required after construction?
Reply #22022-02-15
It applies to manufacturers; that is, 100% radiographic inspection is required for the longitudinal welds before leaving the factory. Regarding the proportion of welding inspections during construction, refer to the requirements specified in the line-list, that is, the pipeline list; inspections should be carried out according to the corresponding inspection level/class indicated in that list.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.