Participation reward: 2 Wealth. Correct reward: 6 Wealth. In the case of cost deviations in a project, the reasons that fall under the owner’s responsibility are ( ).   A. Delayed provision of drawings B. Inappropriate construction plan C. Incomplete construction procedures D. Failure to provide the site in a timely manner E. Use of substitute materials Answer: C, D
Reply #22017-06-01
A cost variance occurred in a certain project; among the causes of this variance, those attributable to the owner are (CD).   A. Delayed provision of drawings B. Inappropriate construction plan C. Incomplete construction procedures D. Failure to provide the site in a timely manner E. Use of substitute materials

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.