[Haichuan Overseas Engineering] 30% model of the FEED phase for the first phase of the Luwuma LNG project in Mozambique has passed the owner’s review

2025-10-24View Original

Thread Content

On October 20, the 30% model of the FEED phase for the Phase 1 LNG project in Ruwuma, Mozambique (referred to as the Mozambique project) was approved by the owner, laying the foundation for striving to secure the EPC contract in the next phase. Since its launch on August 30, 2024, the Southwest Branch has made full use of its design strengths and core technical advantages, organizing professionals in fields such as process engineering, piping, and civil construction to carry out meticulous design work and work closely together in order to overcome challenges such as complex interfaces, stringent technical standards, and frequent adjustments to the overall layout plans and large-scale module designs. Through the efforts of all team members, tasks such as the piping layout for pipes smaller than 6 inches, REVIT forward design for the entire building, calculation and modeling of large-scale structural elements, research on equipment inspection, maintenance, and handling, as well as the layout of buried pipelines and cables, T-shaped walls, and fences were completed efficiently. The level of detail in the design far exceeded the requirements of the 30% stage, creating favorable conditions for the model review. At the review meeting, the Southwest Branch reported on the progress of the 30% model for the project, focusing on the design aspects of the interfaces handled by the company, and the attendees engaged in in-depth discussions. In response to the questions raised by the review committee, the project team provided detailed explanations and responses for each one, earning high recognition from the client and the consortium partners, and passing the 30% model review on the first attempt. Next, the Southwest Branch will continue to adhere to the customer-centric philosophy. Under the leadership of CPECC, it will strengthen communication and cooperation with the relevant parties in the consortium, advance all aspects of the project with high quality, and strive to turn this project into CPECC’s first large-scale modular LNG benchmark overseas. The Phase 1 LNG project in Ruvuma, Mozambique is located in the maritime area of northeastern Mozambique. It is an important part of Mozambique’s Project 4, and it represents a full-industry-chain project that integrates ultra-deep-sea natural gas exploration and development, LNG processing, production, and sales. The main contents of the project are: the FEED design and EPC package for an LNG plant with a capacity of 18 million tons per year, with a contract duration of 16 months. The first phase of the Luwuma LNG project was won through a bid submitted by a consortium consisting of CPECC, Sebun Company, and McDermott Company. Furthermore, the owner will also award the project to another consortium, with one winning bidder ultimately being selected to sign the EPC turnkey contract. CPECC’s main tasks at this stage include: the development of an overall construction plan, the design of administrative areas, certain processes, and custom-made equipment, as well as participation in the research on modular solutions for the entire plant. CPECC organized the West Africa Company and the Southwest Branch to carry out the task together. The Phase 1 LNG project in Ruwuma, Mozambique, is a world-class LNG project in which CPECC participates for the first time in a new capacity. It marks a historic breakthrough for China National Petroleum Corporation in the FEED phase of world-class LNG projects, representing an important step forward in the effort to optimize both the market structure and the business structure. At the same time, the Project in Mozambique’s Region 4 is an important project for CNPC in fulfilling its responsibilities as a central state-owned enterprise, as well as in implementing the Belt and Road Initiative and the dual-carbon strategy. As China National Petroleum Corporation’s most representative international EPC contractor for oil and gas projects, CPECC will make full use of CNPC’s advantages in integrating upstream and downstream operations. By leveraging the highly modular nature of this project as well as China’s well-developed industrial and supply chains, it will effectively integrate the resources of domestic equipment and material suppliers as well as module manufacturers, striving to contribute \"Chinese wisdom\" and \"Chinese strength\" to the construction of this project.
Reply #22025-10-24
18 million tons per year! CPECC Signs Contract for World-Class LNG Project – Chemical New Materials Committee of the Petrochemical Federation, September 1, 2024, 23:59, Beijing. Recently, China Petroleum Engineering Construction Company (CPECC) and its consortium partners successfully signed a service contract for the first phase of the Ruwuma LNG project in Mozambique. The main contents of the project are: the FEED design and EPC package for an LNG plant with a capacity of 18 million tons per year, with a contract duration of 16 months. The project owner, Mozambique Ruwuma Joint Venture (MRV), was established with funding from six companies including ExxonMobil, Eni, and China National Petroleum Corporation; China National Petroleum Corporation is the third-largest shareholder. This project is the first world-class LNG project in which CPECC has participated directly as the general contractor, marking a historic breakthrough for China National Petroleum Corporation in the FEED phase of world-class LNG projects. It is worth noting that the owner also awarded the project to another consortium, with one winner ultimately being selected to sign the EPC turnkey contract.
Reply #32025-10-24
【HaiChuan Overseas Engineering】Significant progress has been made in the installation project of the 50,000 Nm³/h air separation cryogenic tank and storage tank equipment for Cryoinfra company in Mexico. https://bbs.hcbbs.com/thread-5703769-1-1.html (Source: HaiChuan Chemical Forum)
Reply #42025-10-24
【Haichuan Overseas Engineering】The world’s first! Preparatory meeting for the foundation engineering design of Kenya’s 480,000 tons/year green fertilizer and associated geothermal power plant project – https://bbs.hcbbs.com/thread-5703706-1-1.html (Source: Haichuan Chemical Industry Forum)
Reply #52025-10-24
【Ten Years of Rapid Development in Chemical Engineering Equipment】From 2765 to 2025: CGN Group’s technology for the utilization of high-salinity unconventional water resources recognized as internationally leading https://bbs.hcbbs.com/thread-5703353-1-1.html (Source: Haichuan Chemical Industry Forum)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.