Can insulation be applied to a relatively tall tower unit in advance before it is shipped?

2020-11-14View Original

Thread Content

There is a relatively tall tower-type device with a diameter of about two meters and a total height of around 28 meters. It needs to be insulated with rock wool. Considering that scaffolding must be set up for the insulation work on site and that the project delivery deadline is tight, the project manager of the general contractor has requested that the insulation and external protection be applied to the tower device in the workshop before it is shipped. I would like to ask experienced colleagues whether this approach is feasible Normally, we wait on-site until the equipment is in place and the scaffolding is set up before carrying out the insulation work. If that’s feasible, then should the insulation at the equipment’s transportation saddles be done only after the equipment has been lifted into place on-site?
Reply #22020-11-14
1. It can be insulated in the factory, but the cost is high, and damage during transportation can affect its appearance; Moreover, factories may not be willing to rent out their manufacturing facilities to you for insulation work. The manufacturing plant doesn’t have skilled workers for insulation work; it requires you to bring in a team specialized in insulation tasks, which seems quite difficult. 2. Why is it that for a tower over 20 meters tall, scaffolding has to be set up first after it’s in place before insulation work can be carried out? 3. It is recommended to adjust the construction sequence as follows: arrival of equipment, installation of pipelines attached to the tower on the ground, construction of platform ladders and electrical lighting, installation of insulation on the ground, and then overall lifting, so as to achieve a completed structure with all necessary elements in place and the lights turned on once the tower is erected. Doing this saves money, effort, and time, while ensuring high quality and low safety risks.
Reply #32020-11-14
Look at other people's cases. 【In-depth Discussion on Modular Installation by HaiChuan】Modular Lifting of the Stable Tower in Sinopec’s Catalytic Cracking Unit https://bbs.hcbbs.com/thread-2839687-1-1.html (Source: HaiChuan Chemical Forum)
Reply #42020-11-15
A general procedure such as leaving the factory – arriving at the construction site – carrying out anti-corrosion and insulation work on site – and then lifting and installing it seems to me to be a reasonable approach, as it allows for the best possible control over time, risks, speed, and quality.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.