Problems with the sealing of PLAN53B

2021-04-03View Original

Thread Content

How to put PLAN53B seals into use, and what are the precautions?
Reply #22021-04-03
Before operation, check whether the pressure of the accumulator bladder meets the design requirements; during the initial filling and pressurization, exhaust air from the inlet, outlet, and return pipelines separately
Reply #32021-04-03
The accumulator is first filled with nitrogen, and then the system is filled with a isolation fluid
Reply #42021-04-06
1. Adjust the accumulator pressure according to the pressure in the sealing chamber (approximately 80%-85% of the sealing chamber pressure); 2. The barrier fluid must not react with the medium ; 3. Drain the liquid when using the manual fluid replenishment pump to flush ; 4. The pressure should be applied appropriately – it cannot be too high nor too low ; 5. Check the sealing condition of each pipeline ; 6. Manually turn the vehicle over; if there are no abnormalities, start it again

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.