The shaft displacement of Hangzhou Steam Turbine is high

2022-01-25View Original

Thread Content

The turbine is a extraction-type steam turbine; it operates in full condensation mode at the beginning, with the shaft displacement increasing gradually; Random selection will be used later; the displacement remains stable for about 2-3 months ; It’s rising slowly again; I’m asking the experts here to analyze the reasons.
Reply #22022-01-26
It is recommended to measure the thrust bearing clearance and the levelness of the main unit. At this stage, it can only be kept in use; during this time, preparations for the maintenance work need to be planned. For reference.
Reply #32022-01-27
It has been in operation for several years; have you considered the possibility of scaling? What about the pressure in the wheel chamber, the parameters of steam quality, and the operating conditions of the driven machine?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.