A pressure vessel manufactured in 2013 that has been unused until now; it’s brand new. Can it still be used?

2017-01-24View Original

Thread Content

There is a set of equipment manufactured in 2013, but it has not been used yet due to the suspension of the project; it is in brand-new condition. Now that a new project has started, can this equipment be utilized in the new project? The parameters for using the equipment remain unchanged, but many standards have been updated, such as GB713 and JB4731. What procedures are required if we continue to use it?
Reply #22017-01-24
It can be used; a test report issued by the quality inspection agency (Boilery Inspection Institute) as required is sufficient
Reply #32017-01-24
For commissioned testing, the test report and quality certificate shall be submitted together to obtain the use permit
Reply #42017-01-24
I need to go through some procedures at both the Quality Supervision Bureau and the Work Safety Bureau, right?
Reply #52017-01-24
It can be used, but it is necessary to register with the Quality Inspection and Supervision Bureau. A qualified agency should conduct tests and issue a test report, and all equipment must also have their original quality certificates, which are required by the Quality Inspection and Supervision Bureau during inspections.
Reply #62017-01-24
The original design documents and factory quality certification documents must be complete. 1. In accordance with the management requirements for reactivating general equipment, a comprehensive inspection must be carried out first (new equipment should not present any issues), and a report shall be issued ; 2. The design institute shall conduct a review by comparing the original design documents and inspection reports; if possible, it is best to prepare a new set of design documents (after all, they are intended for a new installation), with a consistent project name
Reply #72017-01-24
As long as the operating conditions remain unchanged, it can be used just fine. Remember to register with the special equipment safety management department within 30 days after installing it in a new project before starting to use it; nothing else is an issue:victory:
Reply #82017-01-25
It can be used, but one must go to the special inspection center to complete the relevant procedures.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.