Procedures for shifting pressure vessels

2018-10-16View Original

Thread Content

There is a registered pressure vessel in our facility; later on, since it did not meet the process requirements, we purchased a larger one and placed it in the original equipment’s location, while the old equipment was moved to another place. What procedures are needed for this? Does it be necessary to cancel the previous registration certificate?
Reply #22018-10-16
New ones need to be registered, require installation notifications; some also need to have monitoring systems installed before use registration can be processed. If old equipment is to continue being used, registration changes must be carried out
Reply #32018-10-18
3.8.2.1 Relocation within the administrative jurisdiction of the registration authority: For special equipment that is relocated within the administrative jurisdiction of the registration authority, the user entity shall, prior to putting the equipment into use, submit the original registration certificate, a newly filled out registration form (in two copies), and the inspection report resulting from the relocation (in the case of disassembly and relocation) to the registration authority, in order to apply for a change of registration and obtain a new registration certificate. The registration authority shall make a cancellation mark on the original use registration certificate and the original use registration form.
Reply #42021-03-08
Which standard does this regulation come from?
Reply #52021-03-08
If the equipment information no longer matches the actual conditions after the registration change, such as changes in temperature, pressure, or the medium used, does it still be necessary to modify the original records?
Reply #62021-03-08
It needs to be modified, but this modification has to be carried out by the original design team.
Reply #72021-03-09
Those up there are all experts who just apply pre-established methods mechanically. I would like to ask everyone: what is the installation of pressure vessels?
Reply #82021-03-09
For the relocation of old equipment, relevant relocation procedures are required; for new equipment, notification, inspection, and obtaining a license are necessary before it can be used. It is advisable to work with a qualified installation company. In Jiangsu, we look forward to cooperating with you. Thank you.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.