Materials for pressure vessels generally do not need to be re-inspected upon arrival at the factory, right?

2019-04-09View Original

Thread Content

Once the materials for pressure vessels arrive at the factory, they generally don’t need to be re-inspected, right?
Reply #22019-04-10
Quality assurance engineer determines quality control! We also need to check the design pattern requirements!
Reply #32019-04-10
Material re-inspection shall be carried out for those that meet Clause 5.1 of GB/T150.4 and as required by the drawings; otherwise, material acceptance shall be conducted in accordance with the system requirements.
Reply #42019-04-10
Refer to GB/T150, Pressure Vessel Code
Reply #52019-04-10
Material reinspection shall be carried out in accordance with Clause 5.1 of GB/T150.4 and as required by the drawings. For example, when stainless steel flat sheets are used as the shell of pressure vessels, re-inspection is required.
Reply #62019-04-10
Generally, inspection is not required, but a certificate of conformity from the manufacturer is necessary
Reply #72019-04-10
It can be divided into three types: 1. Whether there are requirements in the drawings or not. 2. Which standard does the product fall under, and what are the requirements of that standard? 3. For those that fall under GB/T150, refer to Article 5 in Part 4, where detailed instructions are provided
Reply #82019-04-19
The regulations and standards do not require it to be done
Reply #92019-04-20
First, check whether your materials fall under clauses 2.1.2 and 2.1.4 of TSG21-2016, as well as clause 5.1.1 of GB150.4-2011. If they meet these requirements, then retesting is necessary; otherwise, it is not required.
Reply #102019-04-22
Re-inspection is required according to standard drinking regulations, for things such as flat plates; for forgings of grade 4 or higher when conditions permit. Re-inspection is generally not required for other components that are not under significant compressive stress
Reply #112019-04-25
There are relevant requirements in GB150 and the fixed capacity regulations; not everything needs to be retested

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.