Is the N3 port of this pipe box designed wrong?

2020-05-04View Original

Thread Content

All the great masters, shouldn’t they open their mouths on the left side?
Reply #22020-05-04
It should be reversed. The number of heat exchange tubes is different. See GBT151, page P19. This is the last type of 8-tube pass. The inlet and outlet should be on one side.
Reply #32020-05-05
First of all, I’m not sure if you are an equipment major. If you are an equipment major, the position of the nozzle is determined by the process major or the piping major, so I would like to ask you about the process.; Secondly, confirm whether this drawing is the final version. If it is the final version, check the design conditions and consult relevant design and review personnel about the considerations of the nozzle position in the drawing.
Reply #42020-05-06
This should be compared with the nozzle orientation diagram. It shows that the orientation of all nozzles is inconsistent. Ask about piping or process.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.