I have a question regarding wire mesh demisters

2022-01-05View Original

Thread Content

When designing separators, especially vertical separators, how is it generally decided whether to install a wire mesh demister? If the wire mesh demister is installed at the top of the tank, should access holes for the maintenance and replacement of the demister be considered? Was this hole designed by the equipment specialists based on the design of the wire mesh demister? Is it necessary to include a separate requirement for the process engineering field in the conditions?
Reply #22022-01-05
It would be best to include a simple diagram to illustrate it; without understanding the principle, it’s impossible to participate in the discussion. This is for reference only.
Reply #32022-01-05
This post was last edited by wanlirn on 2022-1-5 at 16:00. In theory, all separation devices should have a vapor separation unit; it doesn’t have to be a mesh type. We have used swirl-type, baffle-type, corrugated plate-type units, etc., which is why there are so many different types. Perhaps there are indeed differences among them, so it’s best for the process engineering department to specify the requirements; If the textile engineering major chooses a screen, it usually involves specifying the diameter, thickness, and type of wire, such as SP2000-150, as well as the height above the liquid surface ; Generally, they don’t care about whether it’s upper or lower garments, or how the screen is divided into sections or how it needs to be maintained; that still has to be considered by those of us in the equipment field ; In fact, screen maintenance simply involves removing it for cleaning when it gets clogged over time, or replacing it ; Those with a larger diameter can enter and exit; there needs to be a manhole ; The mesh panel has a width of 400–450, and a thickness of 100 or 150. In such cases, a DN600 manhole is required. For devices with a smaller diameter, if the mesh is made of metal, our design includes a flushing system – it can be used to clean the mesh when it gets blocked. If the mesh is made of PE or PTFE, it needs to be replaced after some time; in that case, device flanges are necessary.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.