What data needs to be entered for thermal siphon reboilers in HTRI?

2021-07-16View Original

Thread Content

Dear experts, what parameters need to be entered in the thermal siphon reboiler within HTRI? As shown in the table below, how should the value in the bottommost field be filled in? Thank you
Reply #22021-07-16
It is known that the length of the inlet main pipe is 14,536, with a diameter of 450; the length of the outlet main pipe is 12,349, with a diameter of 800. The diameters at the equipment’s inlet and outlet are 450/450*2. Then, the height of the reboiler return port is 9000 measured from the ground level; the diameter of the reboiler shell is 1200; the distance from the reboiler inlet to the ground level is 1200; and the height of the reboiler liquid level above the ground level is 7000. How should everyone fill in the data regarding height when requesting leave?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.