Is a casing required when underground pipes enter the ground at a peak-shaving station?

2021-03-10View Original

Thread Content

The project owner requires that underground pipes be laid with sleeves when installed beneath the ground. Are there any relevant regulatory requirements for this?
Reply #22021-03-10
It should be considered from an operational perspective, to facilitate inspection, maintenance, and replacement.
Reply #32021-03-11
The client pays to have work done; the person doing the work just needs to take the money and get the job done properly
Reply #42021-03-11
Under no circumstances should the relationship be reversed
Reply #52021-03-11
Well, it still depends on the matter at hand; if it goes against the standard specifications, then design changes are not allowed.
Reply #62021-03-20
The property owner here wants it added, but it doesn’t seem to be required by the petrochemical standards

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.