Issues with filling out the instrument calibration and commissioning records

2018-05-27View Original

Thread Content

As the title suggests, I need to prepare documentation after the maintenance work, and I have some questions for which I hope to get some help: 1. Should the circuitry related to switch valves and electric valves listed in the \"Instrument Index Table\" also be included in the \"Instrument Calibration and Testing Records\"? How should it be filled out? 2. How should the single calibration for on-off valves and electric valves be recorded in the «Valve Calibration Record»? Thank you
Reply #22018-05-28
It involves filling in whether the valve’s operation and status are normal, as well as recording the travel time. That seems to be all
Reply #32019-01-11
Same question: especially the new version 17 has changed a lot compared to before, and it’s really hard to figure out how to fill it out at first.
Reply #42019-01-12
This post was last edited by fjw3081585 on 2019-1-12 at 22:13. I won’t send you the circuit calibration record; it isn’t filled out according to an index table but rather based on the circuit diagram, which should include information such as the circuit diagram number. The form I have here is from the petrochemical industry, and the forms used by the Ministry of Chemical Industry are similar to this one. For control valves and isolation valves, individual testing requires a strength test of the valve, a leakage test, and if there are requirements regarding stroke time, then a record of that stroke time must also be kept, in addition to a gas-tightness test of the diaphragm head. This is something that must be done in accordance with the standards, and it should be reflected in the documents. The loop calibration record needs to be filled in according to the loop number on the circuit diagram; subsequently, the corresponding instrument tag numbers as well as the three measurement points at 0%, 50%, and 100% must also be entered. This is easier to fill out. The problem is that the design institute sometimes doesn’t provide the circuit diagrams, so there are no circuit numbers.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.