2020-07-17View Original

Thread Content

This post was last edited by zxg.wylton on 2020-7-17 at 20:23. As shown in the figure, analyses and explanations are provided separately for the main cable tray supports, branch cable tray supports, and specialized supports for bridge trays: 1. Which departments in the design institute are responsible for the design of items 1 to 4? For example, 4 relates to electricity, instrumentation, telecommunications, or... Which department is responsible for preparing the plans for purchases in 2, 1~4? Describe the situations in design institutes, engineering companies, owners, etc. 3.1~4 Which specialties and teams are responsible for the construction work? Are there any other professional assistance options? 4. Which specialties or departments are responsible for the renovation, maintenance, and management of 1~4 respectively by the owner?
Reply #22020-07-21
1 and 1.2 are tasks for the civil engineering team; conditions need to be provided for them. As for 3.4, the party responsible for the cable tray is the one who should handle it. 2. When purchasing materials, all the materials for various projects are gathered together first; thereafter, it depends on the division of responsibilities – who will be responsible for purchasing the steel channels and other auxiliary materials for your project, and who will handle the purchase of cable trays. This is determined by the terms of your contract. 3. Unknown; those who have worked as contractors are requested to provide additional information. 4. Unknown; those who have worked as owners are requested to provide additional information
Reply #32020-07-25
3. It is the responsibility of the process engineering team; 2 and 3 depend on which professional drawing the steel material is listed in – the team responsible for that drawing will handle it. But generally speaking: if 2–3 are assigned to the electrical or automation fields, and construction and procurement present difficulties, they can be allocated to the process engineering field in the form of construction instructions; 4. Same as 3

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.