Question: Is the configuration program uploaded via the PLC in STEP7 complete?

2024-05-23View Original

Thread Content

This post was last edited by yangbq on 2024-5-23 at 14:16. May I ask the teacher, is the configuration program obtained by uploading it to STEP7 for the ET200S complete? If, after configuration—such as adding devices like a gateway—the software is installed again, will this cause any issues? Thank you!
Reply #22024-05-23
The configuration programs uploaded via the PLC in STEP7 are usually complete, but if you add devices such as gateways after configuration, it is necessary to ensure that all configuration parameters are correct before downloading them, in order to avoid malfunctions. .
Reply #32024-05-23
The program uploaded should be the complete version, including the hardware configuration; if any changes are made, it needs to be recompiled and saved before being downloaded
Reply #42024-05-24
The only downside is that annotations cannot be uploaded back; I’m not sure if this is still the case It hasn’t been used in a long time

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.