This post was last edited by sdscj0122 on 2020-5-31 08:46. It involves multiple-choice questions from the \"Electrical Safety Work Procedures\"; please indicate whether the answer is correct or incorrect. 3 points are awarded for correct answers, 2 points for incorrect ones, and 5 points for a detailed explanation of the reason. A single operation of the pull-cord circuit breaker (switch) can be performed without a work order. Correct
Reply #22020-05-31
Correct: A single operation to close or open a circuit breaker (switch) does not require an operation ticket, but records should be kept after the operation is completed.
Reply #32020-05-31
Correct. The following tasks do not require the use of a du ticket: (1) Accident handling. (2) Single operation to close or open the circuit breaker (switch). (3) Open the grounding switch or remove the only set of grounding wires in the entire station. All of the above operations should be recorded in the operation logbook

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.