2017-01-22View Original

Thread Content

Why is the PSA time set as t1 > t3 and t2 > t4? It’s explained as a way to equalize the pressure in both towers – don’t get it? Please provide an explanation
Reply #22017-01-22
Where was it designed, and what is the manufacturing process? The PSA systems of different design institutes are distinct, and the meaning of time also varies
Reply #32017-01-22
What do T1, T2, T3, and T4 each represent? T2 should be included within the time frame of T1, and it must meet the minimum time requirement for this step
Reply #42017-01-23
Different design institutes use different ways to divide PSA time slots; the original poster should send us a timing table so that we can study it. Different numbers of voltage equalization cycles imply different meanings as well. I hope the original poster can post a picture so we can learn from it*.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.