[Engineering Version] Daily Question 20180501

2018-05-01View Original

Thread Content

A certain sub-project involves 3 construction processes, which are organized into 4 construction sections with equal flow rhythms to carry out accelerated multiplicative-rhythm flow construction. Given that the flow rhythms for each construction process are 6, 4, and 4 days respectively, what are the flow step distance and the number of specialized work teams? ( )   A、6 days and 3   B、4 days and 4   C、4 days and 3   D、2 days and 7 Answer: D

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.