【Daily Question】Production Version - Storage and Transportation Operations - 20190130

2019-01-30View Original

Thread Content

For newly built, overhauled, and reinstalled tanks, calibration can only be carried out after filling them with water to at least ( ) of their total capacity and waiting for ( ) hours. Correct answer: 80% ; 72
Reply #22019-01-30
Cylinders that have been newly constructed, overhauled, or reinstalled must wait for (72) hours after being filled with water to at least 80% of their full capacity before they can be inspected.
Reply #32019-01-30
Over 80%, and maintained for 72 hours

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.