Our factory is under construction, so 30871 does not apply; there is no need to obtain those 8 types of permits. Are there any similar permits that need to be obtained?
Reply #22020-05-29
It applies also during construction; however, since there are relatively few flammable, combustible, toxic, or corrosive materials, the risks of fires, explosions, poisoning, and asphyxiation are relatively low, resulting in fewer safety measures being required compared to those necessary during plant production. However, there are many types of operations such as lifting operations, work in confined spaces, groundwork, circuit interruption work, temporary power usage, and work at heights; moreover, these operations often involve simultaneous carrying out of multiple tasks, which increases the risks associated with them. Therefore, strict adherence to GB30871 is very beneficial for reducing such risks.
Reply #32020-05-29
But it’s not possible to issue tickets for this; if such tickets were to be issued, risk assessments would have to be conducted every morning, and it would be necessary to decide which locations at heights need lifting work to be carried out that day
Reply #42020-05-29
During the project construction phase, operations such as lifting, work in confined spaces, excavation and welding, circuit disconnection, temporary power use, and work at heights are subject to the \"Detailed Rules for Project Management\" attached to the \"Project Contract\" (or similar project management procedures and regulations specified in the contract). When the factory enters the trial operation or commissioning phase, it must comply strictly with GB 30871 \"Safety Specifications for Special Operations in Chemical Production Units\".
Reply #52020-05-29
The true intention has been revealed: it’s because they find themselves/their department a hassle.
Reply #62020-06-01
Yes, it takes several hours just to handle the tickets
Reply #72020-06-03
According to GB30871, for production facilities under construction, hot work can be approved as class II hot work, with a maximum duration of 72 hours; The time requirements for other special operations (such as temporary power use) are relatively more flexible, but inspections and documentation for work in confined spaces as well as for hot work must be carried out strictly. For tasks that take place over large areas, it is possible to assign dedicated personnel to conduct regular inspections on a daily basis and keep records. Daily risk assessment is a requirement of safety management; it should be conducted on a daily basis both during the construction phase and once operations begin. Each construction team is responsible for submitting reports based on the construction plan the day before, which are then compiled and submitted by the safety management department. Larger lifting operations, earthwork projects, and circuit-breaking tasks should be managed as individual projects, with construction plans and schemes prepared for approval; risk assessment and control are carried out based on these plans and schemes. During the installation phase, temporary power usage and work at heights involve a wide range of aspects and involve complex and diverse processes; therefore, a comprehensive risk analysis should be conducted before formulating an overall work plan. Specific safety measures should be established, and in particular, stricter management is required for scaffolding work, with dedicated personnel assigned to carry out inspections and verifications. If blind plate installation and removal is involved, the risk is relatively low since no hazardous substances are present. During pressure testing of pipeline equipment, it is important to ensure proper pressure relief when removing or installing these plates. All temporary blind plates used should be properly recorded; failure to do so could lead to serious accidents once the system is put into operation.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.