2021-03-22View Original

Thread Content

We are currently working on the trial production plan, and we’re not sure whether to include the purge gas sealing plan in it. In HG20231, no specific requirements are given; only the general framework is outlined, with no detailed implementation plans provided. So should it be included? The manager says it needs to be added. But those written by other companies on the Internet also did not include specific plans. I would like to ask the seniors for advice
Reply #22021-03-22
This post was last edited by altpage on 2021-3-22 at 15:14. Please refer to the requirements outlined in Document No. 45 on work safety: Article 22 stipulates that the project owner shall organize relevant units involved in the design, construction, and supervision of the project, as well as experts, to identify potential safety issues and corresponding countermeasures that may arise during the trial production (use) of the project (hereinafter referred to as trial production/use). A comprehensive plan for trial production/use shall be developed in accordance with relevant laws, regulations, rules, **standards, and industry standards related to work safety. The trial production (operation) plan shall include the following elements related to safe production: (1) The completion status of production preparations such as pressure testing, purging, airtightness testing of equipment and pipelines in the construction project, individual unit testing, instrument calibration, and joint commissioning ; (II) Feed-in commissioning plan ; Preparing the purge gas tightness plan and carrying out the work according to that plan constitutes the completion of the production preparation tasks.
Reply #32021-03-22
“Regulations on Production Preparation and Commissioning for PetroChina’s Construction Projects”, PetroChina Jian [2011] No. 897; the scope of commissioning includes purging for airtightness testing.
Reply #42021-04-22
This is certain; the trial production plan needs to be reviewed and filed

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.