Vacuum pumping step in the vacuum distillation tower

2018-11-19View Original

Thread Content

The process is as follows: vacuum tower top gas -> primary steam vacuum pump -> secondary steam vacuum pump -> water ring vacuum pump! Is the procedure to first complete the previous steps: start the water ring pump, then turn on the primary steam for vacuuming, and finally the secondary one? ? ?
Reply #22018-11-19
Start the water ring pump, stage 2 first, then stage 1
Reply #32018-11-19
For steam evacuation, are there any requirements regarding the sequence of stage 1 and stage 2?
Reply #42018-12-01
Start the water ring pump first; once the pressure is stable, start the secondary vacuum pump. Generally, these two units are sufficient to meet the production requirements. The primary vacuum pump consumes a large amount of steam and has high energy consumption, so its use is determined based on the production needs – specifically, whether deeper vacuum levels are required.
Reply #52019-02-19
When starting, it is always done from back to front, such as level 3, level 2, level 1.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.