What precautions should be taken during the installation of tower internals?

2010-06-30View Original

Thread Content

What are the installation standards for float valves and liquid drop plate support rings during the installation of tower internals?
Reply #22010-06-30
Being straight and level are basic requirements; the spacing, gaps, bottom clearance, and the height of the inlets and outlets must all be adjusted in accordance with the specified dimensions. It is recommended to hire a skilled blacksmith for this task.
Reply #32010-06-30
Most importantly, make sure not to damage the float valve or cause it to become loose; otherwise it will fall off after driving for a short while! Aren’t the internal components all installed by the manufacturer itself? It can be accepted in accordance with the tray technology requirements 1205 ; The bottom clearance, outlet weir, inlet weir, etc. are basically as they are; major deviations generally cannot be adjusted during installation ;

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.