Are pumps usually installed on the first floor?

2015-09-29View Original

Thread Content

As the title suggests, regardless of whether the conveying equipment is on the second floor or the third floor, should the pump be placed on the first floor?
Reply #22015-09-29
It’s not necessarily the case; it depends on the operating conditions. Several of our company’s pumps are installed on 20-meter-high frames, but they don’t have as good stability as those placed on the ground! ! ! ! ! ! ! ! ! ! ! !
Reply #32015-09-29
Pumps that are too large are probably not suitable for placement on upper floors; some compressors may appear to be on the second floor, but their huge foundations still start underground.
Reply #42015-09-29
Pumps generally experience significant vibration during operation; the vibration is even greater when they are installed on upper floors, which can affect their performance as well as that of other equipment. It also increases the requirements regarding the installation foundation, as well as the building’s vibration resistance and damping capabilities. Therefore, it is advisable to install pumps on the ground floor whenever possible, as this ensures smoother operation of the pumps. This is my personal understanding for reference only.
Reply #52015-09-29
The first floor helps to prevent vibrations from damaging the base valves, and it also facilitates inspections by on-site personnel, as the lower location makes suction easier
Reply #62015-09-29
Not necessarily; vacuum pumps are usually placed on the upper floor. It doesn’t matter for small pumps, but it’s easier to install large pumps on the ground floor. Moreover, it’s very convenient to carry out maintenance on the first floor; if repairs need to be done upstairs, a crane is required, which is quite troublesome. We even place those vacuum pumps that require frequent maintenance on the ground
Reply #72015-09-29
Then more piping will be used
Reply #82015-09-29
Well, I’m referring to normal circumstances; special situations are obviously different
Reply #92015-09-29
To repair a pump, a crane is necessary; you’re referring to those very large pumps, right?
Reply #102015-09-29
Compared to laying the foundation (since the pump is not on the same floor), especially for large pumps, this amount of piping isn’t much of a concern
Reply #112015-09-29
There are many on the first floor; a few small pumps are also located on the second floor. In such cases, the convenience of operation also needs to be taken into consideration, for example regarding the filtration and pressure-boosting pumps

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.