I’ve gathered some questions from this year’s First-Class Constructor exam, along with their answers. I’m sharing them here to boost everyone’s interest in participating. Instead of posting them all at once, I’ll present a few multiple-choice questions or one case study at a time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; the moderator will give a reward for correct answers. ******************************************9. The functional coefficients and cost coefficients of the four mutually exclusive construction plans are shown in the table below. From the perspective of value engineering, the optimal solution has a function coefficient of 1.20, 1.25, 1.05, or 1.15, and a cost coefficient of 1.15, 1.01, 1.05, or 1.20. Options: A. A; B. B; C. C; D. D. Answer: B. 【Expert Explanation】The optimal solution is the one with the highest value coefficient. The value coefficient is calculated as the functional evaluation value divided by the actual functional cost. Another way to calculate it is by using the function coefficient divided by the cost coefficient. However, this method isn’t covered in the textbook at all; therefore, this question goes slightly beyond the scope covered in the textbook. Nevertheless, based on the information given, the only approach available is to divide the values in the first row by those in the second row to determine which value is the highest. Refer to the textbooks for cost engineers or those dedicated to engineering economics. 10. When preparing the bill of quantities, the tenderer should add items that are not covered by the current (measurement standards) for various types of work. Regarding the coding of such additional items, which statement is correct? A. The code for such an item should consist of the code from the relevant measurement standard along with three Arabic digits. B. The person who prepares the bill of quantities should submit these additional items to the provincial or industry-based engineering cost management authority for record-keeping. C. The person preparing the bill of quantities can simply add these items after the last listed item, without assigning a code to them. D. Such items should be coded using the code of a similar item as specified in the measurement standards. Answer: B 【Expert Explanation】The basic principles for coding such additional items can be found on page 229 of the textbook. In option A, there is an additional element between the code and the three Arabic digits ; The errors in C and D can also be determined to be wrong based on common sense.
9. The functional coefficients and cost coefficients of the four mutually exclusive construction plans are shown in the table below. From the perspective of value engineering, the optimal option is B. When preparing the bill of quantities, the tenderer should add items that are not covered by the current measurement standards for various types of work; regarding such additional items and their codes, the correct statement is B: the person responsible for preparing the bill of quantities should submit these additional items to the provincial or industry-based engineering cost management authorities for record-keeping
9. The functional coefficients and cost coefficients of the four mutually exclusive construction plans are shown in the table below. From the perspective of value engineering, the optimal option is B: Function coefficient – 1.20, 1.25, 1.05, 1.15; Cost coefficient – 1.15, 1.01, 1.05, 1.20. A. A B. B C. C D. D 10. When preparing the bill of quantities, the tenderer must add items that are not covered by the current measurement standards for various types of work. Regarding such additional items and their codes, the correct statement is B. A. The code for such an item should consist of the code from the relevant measurement standard along with three Arabic digits. B. The person who prepares the bill of quantities should submit these additional items to the provincial or industry-based cost management authority for record-keeping. C. The person preparing the bill of quantities can simply add these items after the last listed item, without assigning them a code. D. Such items should be assigned codes based on those of similar items in the measurement standards
9. The functional coefficients and cost coefficients of the four mutually exclusive construction plans are shown in the table below. From the perspective of value engineering, the optimal solution is: function coefficients of 1.20, 1.25, 1.05, 1.15; cost coefficients of 1.15, 1.01, 1.05, 1.20. Options: A. A; B. B; C. C; D. D. The correct answer is C. 10. When preparing the bill of quantities, the employer must include those items that are not covered by the current measurement standards for various types of work. Regarding such supplementary items and their codes, which statement is correct? A. The code for such an item should consist of the code from the relevant measurement standard along with three Arabic digits. B. The person responsible for preparing the bill of quantities should submit these supplementary items to the provincial or industry-based engineering cost management authority for record-keeping. C. The person preparing the bill of quantities can simply add these items after the last listed item, without assigning them a code. D. Such items should be assigned codes based on similar items listed in the measurement standards. The correct answer is B
9. The functional coefficients and cost coefficients of the four mutually exclusive construction plans are shown in the table below. From the perspective of value engineering, the optimal option is B: Function coefficient – 1.20, 1.25, 1.05, 1.15; Cost coefficient – 1.15, 1.01, 1.05, 1.20. A. A B. B C. C D. D 10. When preparing the bill of quantities, the tenderer must add items that are not covered by the current measurement standards for various types of work. Regarding such additional items and their codes, the correct statement is B. A. The code for such an item should consist of the code from the relevant measurement standard along with three Arabic digits. B. The person who prepares the bill of quantities should submit these additional items to the provincial or industry-based cost management authority for record-keeping. C. The person preparing the bill of quantities can simply add these items after the last listed item, without assigning them a code. D. Such items should be assigned codes based on those of similar items in the measurement standards
9. The functional coefficients and cost coefficients of the four mutually exclusive construction plans are shown in the table below. From the perspective of value engineering, the optimal solution is as follows: Function coefficient for option B is 1.20, 1.25, 1.05, 1.15; cost coefficient is 1.15, 1.01, 1.05, 1.20. A. A B. B C. C D. D 10. When preparing the bill of quantities, the tenderer must add items that are not covered by the current measurement standards for various types of work. Regarding these additional items and their codes, the correct statement is B. A. The code for such an item should consist of the code from the relevant measurement standard along with three Arabic digits. B. The person who prepares the bill of quantities should submit these additional items to the provincial or industry-based engineering cost management authority for record-keeping. C. The person preparing the bill of quantities can simply add these items after the last listed item, without assigning them a code. D. Such items should be assigned codes based on those of similar items in the measurement standards
The functional coefficients and cost coefficients of the four mutually exclusive construction plans are shown in the table below. From the perspective of value engineering, the optimal solution is B. Option B
10. When preparing the bill of quantities, the tenderer should add items that are not covered by the current (measurement standards) for various types of work. Regarding such additional items and their codes, the correct statement is (b): B. The person responsible for preparing the bill of quantities should submit these additional items to the provincial or industry-based engineering cost management authorities for record-keeping
9. B. B 10. B. The list compiler shall submit supplementary items to the provincial or industry-based engineering cost management authorities for record-keeping