Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. During the foundation excavation phase of a construction project, unfavorable soft soil layers were encountered, requiring foundation treatment; this slowed down the construction progress and increased costs. This type of risk falls under ( ). A. Organizational risks B. Technical risks C. Engineering environment risks D. Economic and management risks 【Production and Management Division】Seeking moderators and technical discussants to join
C. Engineering environmental risks-----------------------------------
During the foundation excavation phase of a construction project, unfavorable soft soil layers were encountered, requiring foundation treatment; this slowed down the construction progress and increased costs. This risk falls under (C). A. Organizational risk B. Technical risk C. Engineering environment risk D. Economic and management risk
This risk belongs to (C, Engineering environmental risk).
C, Engineering environmental risks ~~~~~~~~~~~~~~~~~~~~~
During the foundation excavation phase of a construction project, unfavorable soft soil layers were encountered, requiring foundation treatment; this delayed the construction progress and increased costs. This risk falls under (C). A. Organizational risk B. Technical risk C. Engineering environment risk D. Economic and management risk
During the foundation excavation phase of a construction project, unfavorable soft soil layers were encountered, requiring foundation treatment; this delayed the construction progress and increased costs. This risk falls under (c). A. Organizational risk B. Technical risk C. Engineering environment risk D. Economic and management risk
C. Engineering environmental risks. :victory::victory::victory:
Hehe, finally I noticed a spelling mistake. What does “dislike for the project duration” mean? ? ------------------------- During the foundation excavation phase of a construction project, unfavorable soft soil layers were encountered, requiring foundation treatment; this delayed the construction progress and increased costs. This risk falls under (c). A. Organizational risk B. Technical risk C. Engineering environment risk D. Economic and management risk This question focuses on risks and the magnitude of those risks. Engineering environmental risks include: natural disasters ; Geological and hydrogeological conditions of rocky terrain ; Weather conditions ; Factors that cause fires and explosions, etc.
During the foundation excavation phase of a construction project, unfavorable soft soil layers were encountered, requiring foundation treatment; this slowed down the construction progress and increased costs. This risk falls under (C).