Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. To achieve optimal results in cost management, the organizational measures that a project manager can take are ( ). A. Strengthen construction scheduling to avoid idle labor losses. B. Conduct technical and economic analyses to determine the best construction plan. C. Implement owner’s approvals for various changes in a timely manner. D. Study contract terms to identify opportunities for claims. [Production and Management Division] Seeking moderators and technical discussants to join
Reply #22015-11-05
To achieve optimal results in cost management, the organizational measure that a project manager can take is (A). A. Strengthen construction scheduling to avoid downtime losses. B. Conduct technical and economic analyses to determine the best construction plan. C. Implement owner’s approvals for various changes in a timely manner. D. Study contract terms to identify opportunities for claims
Reply #32015-11-05
A. Strengthen construction scheduling to avoid idle labor losses
Reply #42015-11-05
A. Strengthen construction scheduling to avoid idle labor losses
Reply #52015-11-05
To achieve optimal results in cost management, the organizational measures that a project manager can take are (A). A. Strengthening construction scheduling to avoid losses due to idle time; B. Conducting technical and economic analyses to determine the best construction approach; C. Promptly obtaining owner approvals for any changes; D. Studying the contract terms to identify opportunities for claims
Reply #62015-11-05
To achieve optimal results in cost management, the organizational measure that a project manager can take is (A)
Reply #72015-11-05
To achieve optimal results in cost management, the organizational measure that project managers can take is (A: improving construction scheduling to avoid downtime losses).
Reply #82015-11-05
To achieve optimal results in cost management, the organizational measure that a project manager can take is (A).
Reply #92015-11-05
To achieve optimal results in cost management, the organizational measure that a project manager can take is (B). A. Strengthen construction scheduling to avoid downtime losses. B. Conduct technical and economic analyses to determine the best construction plan. C. Implement owner’s approvals for various changes in a timely manner. D. Study contract terms to identify opportunities for claims
Reply #102015-11-05
Choose ABC. . . . . . . . . .
Reply #112015-11-05
To achieve optimal results in cost management, the organizational measure that a project manager can take is (A).

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.