Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. A construction company won the contract to carry out a certain project through bidding. After the contract was signed, the relevant departments of the company began to assign a project manager and prepare a cost plan. The cost plan prepared at this stage belongs to ( ). A. Competitive cost planning B. Guiding cost planning C. Implementative cost planning D. Strategic cost planning 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22015-11-06
A construction company won the contract to carry out a certain project through bidding. After the contract was signed, the relevant departments of the company began to assign a project manager and prepare a cost plan. The cost plan prepared at this stage belongs to (B). A. Competitive cost planning B. Guiding cost planning C. Implementative cost planning D. Strategic cost planning
Reply #32015-11-06
A construction company won the contract to carry out a certain project through bidding. After the contract was signed, the relevant departments of the company began to assign a project manager and prepare a cost plan. The cost plan prepared at this stage belongs to (b). A. Competitive cost planning B. Guiding cost planning C. Implementative cost planning D. Strategic cost planning
Reply #42015-11-06
A construction company won the contract to carry out a certain project through bidding. After the contract was signed, the relevant departments of the company began to assign a project manager and prepare a cost plan. The cost plan prepared at this stage is a (B, guiding cost plan).
Reply #52015-11-06
Select the answer: B, Guiding cost plan
Reply #62015-11-06
A construction company won the contract to carry out a certain project through bidding. After the contract was signed, the relevant departments of the company began to assign a project manager and prepare a cost plan. The cost plan prepared at this stage belongs to (B). A. Competitive cost planning B. Guiding cost planning C. Implementative cost planning D. Strategic cost planning
Reply #72015-11-06
C、-------------------------------------------------
Reply #82015-11-06
B, Guiding cost plan :victory::victory:
Reply #92015-11-06
A construction company won the contract to carry out a certain project through bidding. After the contract was signed, the relevant departments of the company began to assign a project manager and prepare a cost plan. The cost plan prepared at this stage belongs to (b). B, Guiding cost plan
Reply #102015-11-06
The cost plan prepared at this stage is a (B, guiding cost plan).
Reply #112015-11-06
A construction company won the contract to carry out a certain project through bidding. After the contract was signed, the relevant departments of the company began to assign a project manager and prepare a cost plan. The cost plan prepared at this stage belongs to (B).

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.