This post was last edited by yuchenchf on 2015-11-12 at 16:38. Reward for participation: 2 Wealth. Reward for correct answer: 9 wealth. In accordance with the Standard Construction Bidding Documents, for those parts of the work that are concealed when the supervisor fails to conduct inspections within the agreed time and no other instructions are given, the contractor carries out the concealment on their own. Thereafter, re-inspection after peeling revealed that its quality met the contractual requirements; therefore, the additional costs and the delay in the project timeline shall be borne by ( ). A. Contractor B. Client C. Both the client and the contractor D. The supervisor and the contractor together 【Production and Management Division】Seeking moderators and technical discussants to join
Reply #22015-11-12
---------------B, the employer------------------
Reply #32015-11-12
In accordance with the Standard Construction Bidding Documents, for those parts of the work that are concealed when the supervisor fails to conduct inspections within the agreed time and no other instructions are given, the contractor carries out the concealment on their own. Thereafter, re-inspection after stripping revealed that its quality met the contractual requirements; thus, the additional costs and the delay in the project timeline shall be borne by (B).
Reply #42015-11-12
In accordance with the Standard Construction Bidding Documents, for those parts of the work that are concealed when the supervisor fails to conduct inspections within the agreed time and no other instructions are given, the contractor carries out the concealment on their own. Thereafter, re-inspection after stripping revealed that its quality met the contractual requirements; therefore, the additional costs and delays in the project timeline shall be borne by (B, the employer).
Reply #52015-11-12
In accordance with the Standard Construction Bidding Documents, for those parts of the work that are concealed when the supervisor fails to conduct inspections within the agreed time and no other instructions are given, the contractor carries out the concealment on their own. Thereafter, re-inspection after peeling showed that its quality met the contract requirements; the resulting additional costs and delay in the project timeline shall be borne by (b).
Reply #62015-11-12
DDDDDDDDDDDDDDDDDDD
Reply #72015-11-12
B. Contract issuance.........................
Reply #82015-11-12
In accordance with the Standard Construction Bidding Documents, for those parts of the work that are concealed when the supervisor fails to conduct inspections within the agreed time and no other instructions are given, the contractor carries out the concealment on their own. Thereafter, re-inspection after stripping revealed that its quality met the contractual requirements; thus, the additional costs and the delay in the project timeline shall be borne by (B). A. Contractor B. Employer C. Employer and contractor jointly D. Supervisor and contractor jointly
Reply #92015-11-12
In accordance with the Standard Construction Bidding Documents, for those parts of the work that are concealed when the supervisor fails to conduct inspections within the agreed time and no other instructions are given, the contractor carries out the concealment on their own. Thereafter, re-inspection after stripping revealed that its quality met the contract requirements; therefore, the additional costs and delays in the project timeline shall be borne by (B)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.