Let’s work on question 80 of 2015’s First-Class Constructor Exam – multiple-choice question 66 from the \"Project Management\" section; there will be a reward for those who answer it correctly. Those who do these questions every day are truly eager learners! ! Today marks the start of the project management series – welcome to join! *************************************************I have gathered some questions from this year’s First-Class Constructor exam, along with their answers. I’m sharing them here to increase everyone’s interest in participating. Instead of posting them all at once, I’ll present a few multiple-choice questions or one case study at a time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; those who give correct answers will receive rewards from the moderators. ******************************************After completing the questions, it’s time to rest, and enjoying delicious food is the best way to do that. Everyone is encouraged to click on the posts related to food topics: a summary post of the “Food Search” series. Feel free to share your own ideas as well, and you’re also welcome to join discussions in the safety-related section. Fun posts about traffic violations – summary post. ******************************************66. Which of the following statements regarding the general contracting management model for construction projects is correct? ( ) A. The general construction management contractor shall be involved in the construction of all specific projects. B. When issuing a tender for a general construction management contractor, the owner should first determine the total cost of the project. C. The general construction management contractor is responsible for the tendering process for all subcontracting contracts. D. The owner does not need to wait until the construction drawings are completed before issuing a tender for a general construction management contractor. 【Standard answer】D
B. When the owner issues a tender for the general construction management contractor, the total cost of the project should be determined first
C. The general construction management unit is responsible for the bidding process for all subcontracting contracts
Regarding the general contracting management model for construction projects, the correct statement is (d). D. The owner does not need to wait for the completion of the construction drawings before bidding for a general construction management contractor
66. Regarding the general contracting management model for construction projects, the correct statement is (D). A. The general construction management contractor shall be involved in the construction of all specific projects. B. When inviting bids for a general construction management contractor, the owner should first determine the total cost of the project. C. The general construction management contractor is responsible for the bidding process for all subcontracts. D. The owner does not need to wait until the construction drawings are completed before inviting bids for a general construction management contractor
D. The owner does not need to wait for the completion of the construction drawings before bidding for a general construction management contractor
A. The general construction management contractor shall be involved in the construction of all specific projects
D. The owner does not need to wait for the completion of the construction drawings before bidding for a general construction management contractor
A. The general construction management contractor shall be involved in the construction of all specific projects