The three simultaneities for environmental assessment of new construction projects?

2015-11-27View Original

Thread Content

Is the environmental assessment for new chemical projects similar to that for safety, involving preliminary environmental evaluation, design review, acceptance evaluation, and status assessment?
Reply #22015-11-27
Construction projects must strictly comply with the laws regarding environmental impact assessment and the \"three simultaneities\" principle, that is, safety pre-assessment, safety acceptance assessment, and safety status assessment must all be carried out simultaneously.
Reply #32015-11-27
The principle of \"three simultaneities\" means that the environmental protection facilities for a construction project must be designed, constructed, and put into use simultaneously with the main project itself
Reply #42015-11-27
View documents such as the Environmental Protection Regulations for construction projects and related classification catalogs. Reference
Reply #52015-11-29
Construction projects must strictly comply with the laws regarding environmental impact assessment and the \"three simultaneities\" principle, that is, safety pre-assessment, safety acceptance assessment, and safety status assessment must all be carried out simultaneously.
Reply #62015-11-29
The concept of \"simultaneous implementation of environmental protection measures\" mainly involves the following stages: the project feasibility study stage (for projects that are not environmentally friendly, an environmental impact assessment must be carried out at this stage; for environmentally friendly projects, the assessment can be done during the preliminary design phase), the preliminary design stage (an environmental impact assessment is required at this stage), the project construction stage (ensuring that environmental protection facilities are constructed simultaneously with the main structure of the project), the trial production stage (trial production must be registered within three months), and project acceptance (environmental monitoring is conducted).
Reply #72015-12-29
But I heard that for environmental impact assessments, there are only two stages: design and acceptance. Is that correct?
Reply #82016-01-04
Just look up the detailed environmental protection regulations and you’ll have it

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.