Thread Content
Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Multiple-choice question: According to the \"Code for Quantity Calculation and Pricing of Construction Projects\" (GB50500-2013), which of the following statements regarding daily rates are correct? A. The employer shall notify the contractor of any miscellaneous tasks to be carried out on a day-rate basis, and the contractor must carry out such tasks. B. For any change order that is priced on a day-rate basis, the contractor must submit the relevant reports and documents to the employer for review. C. Within 2 days of receiving the site visa reports submitted by the contractor, the employer shall confirm the summary of the day-rate records. D. Day-rate pricing is a method used by the contractor to calculate the cost of miscellaneous tasks within the scope of the contract, based on the unit prices specified in the contract. E. At the end of each payment period, the contractor must submit to the employer a summary table of all day-rate records for that period. 【Haichuan Thanksgiving】– Production Division 【Production and Management Division】is seeking moderators and technical discussants to join us
According to the \"Code for Quantification of Construction Works and Pricing\" (GB50500-2013), the correct statements regarding daily rates are (A B C E). A. The employer shall notify the contractor of any incidental tasks to be carried out on a daily rate basis, and the contractor must carry out such tasks. B. For any change order that is priced on a daily rate basis, the contractor must submit the relevant reports and documents to the employer for review. C. Within 2 days of receiving the site visa reports submitted by the contractor, the employer shall confirm the summary of the daily rate records. D. Daily rates represent a method of pricing incidental tasks carried out by the contractor within the scope of the contract, in accordance with the unit prices specified in the contract. E. At the end of each payment period, the contractor must submit to the employer a summary table of all daily rate records for that period
ABCE daily rate pricing is a method used during construction, whereby the contractor carries out miscellaneous tasks or works other than those specified in the construction drawings provided by the employer, and the cost is calculated based on the comprehensive unit price agreed upon in the contract.
According to the \"Code for Quantification of Construction Works and Pricing\" (GB50500-2013), the correct statements regarding daily rates are (A B C E). A. The employer shall notify the contractor of any incidental tasks to be carried out on a daily rate basis, and the contractor must carry out such tasks. B. For any change order that is priced on a daily rate basis, the contractor must submit the relevant reports and documents to the employer for review. C. Within 2 days of receiving the site visa reports submitted by the contractor, the employer shall confirm the summary of the daily rate records. D. Daily rates represent a method of pricing incidental tasks carried out by the contractor within the scope of the contract, in accordance with the unit prices specified in the contract. E. At the end of each payment period, the contractor must submit to the employer a summary table of all daily rate records for that period
According to the \"Code for Quantity Calculation and Pricing of Construction Projects\" (GB50500-2013), the correct statements regarding daily rates are (ABCE). A. The employer shall notify the contractor of any incidental tasks to be carried out on a daily rate basis, and the contractor must carry out such tasks. B. For any change order that is priced on a daily rate basis, the contractor must submit the relevant reports and documents to the employer for review. C. Within 2 days of receiving the site visa reports submitted by the contractor, the employer shall confirm the summary of the daily rate records. D. Daily rates represent a method of pricing incidental tasks carried out by the contractor within the scope of the contract, in accordance with the unit prices specified in the contract. E. At the end of each payment period, the contractor must submit to the employer a summary table of all daily rate records for that period
A. The employer shall notify the contractor of any minor tasks to be carried out on a daily rate basis, and the contractor must carry out such tasks. B. For any change order that is priced on a daily rate basis, the contractor must submit the relevant reports and documents to the employer for review. C. Within 2 days of receiving the site visa reports submitted by the contractor, the employer shall confirm the summary of the daily rate records. E. At the end of each payment period, the contractor shall submit to the employer a summary table of all daily rate records for that period