Participation reward: 2 Wealth. Reward for correct answer: 9 wealth. Which of the following statements is correct regarding the project management tasks of the general construction contractor? ( ) A. The general construction contractor generally does not undertake the actual construction work; it is only responsible for the overall management and coordination of the construction process. B. The general construction contractor is only accountable for the construction safety of the areas it is responsible for, and it bears no responsibility for the construction safety of subcontractors appointed by the owner. C. The general construction contractor does not sign construction contracts directly with subcontractors; such contracts are signed by the owner. D. The general construction contractor is responsible for organizing the supply of construction resources. 【Haichuan Thanksgiving】– Production Division 【Production and Management Division】is seeking moderators and technical discussants to join us
Reply #22016-03-17
D. The general contractor for the construction shall be responsible for organizing the supply of construction resources
Reply #32016-03-17
Regarding the project management tasks of the general construction contractor, the correct statement is (D). A. The general construction contractor generally does not undertake the actual construction work; it is only responsible for the overall management and coordination of the construction process. B. The general construction contractor is only accountable for the construction safety of the sections it is responsible for, and it bears no responsibility for the construction safety of subcontractors appointed by the owner. C. The general construction contractor does not enter into construction contracts directly with subcontractors; such contracts are all signed by the owner. D. The general construction contractor is responsible for organizing the supply of construction resources
Reply #42016-03-17
D. The general contractor for the construction shall be responsible for organizing the supply of construction resources
Reply #52016-03-17
Regarding the project management tasks of the general construction contractor, the correct statement is (D). A. The general construction contractor generally does not undertake the actual construction work; it is only responsible for the overall management and coordination of the construction process. B. The general construction contractor is only accountable for the construction safety of the sections it is responsible for, and it bears no responsibility for the construction safety of subcontractors appointed by the owner. C. The general construction contractor does not enter into construction contracts directly with subcontractors; such contracts are all signed by the owner. D. The general construction contractor is responsible for organizing the supply of construction resources
Reply #62016-03-17
The general construction contractor shall be responsible for organizing the supply of construction resources
Reply #72016-03-17
Regarding the project management tasks of the general construction contractor, the correct statement is (D). A. The general construction contractor generally does not undertake the actual construction work; it is only responsible for the overall management and coordination of the construction process. B. The general construction contractor is only accountable for the construction safety of the sections it is responsible for, and it bears no responsibility for the construction safety of subcontractors appointed by the owner. C. The general construction contractor does not enter into construction contracts directly with subcontractors; such contracts are all signed by the owner. D. The general construction contractor is responsible for organizing the supply of construction resources
Reply #82016-03-17
Regarding the project management tasks of the general construction contractor, the correct statement is (D). A. The general construction contractor generally does not undertake the actual construction work; it is only responsible for the overall management and coordination of the construction process. B. The general construction contractor is only accountable for the construction safety of the sections it is responsible for, and it bears no responsibility for the construction safety of subcontractors appointed by the owner. C. The general construction contractor does not enter into construction contracts directly with subcontractors; such contracts are all signed by the owner. D. The general construction contractor is responsible for organizing the supply of construction resources

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.