【Daily Question】Chemical Engineering Principles 365: Boiler Overhaul (April 28)

2016-04-28View Original

Thread Content

The Chemical Engineering Theory section is launching the \"One Question per Day\" campaign starting today, aimed at helping everyone reinforce their basic knowledge in chemical engineering. Subsequent series will include those on \"Principles of Chemical Engineering,\" \"Mass Transfer and Separation,\" \"Thermodynamics in Chemical Engineering,\" and \"Chemical Process Engineering.\" We hope you will give it your active support! Wishing you a happy Christmas! Answers to the questions in the \"One Question per Day\" campaign can be viewed directly by replying to the post, and the thread will be closed after 1 day ! To encourage continued participation from everyone this year! You get 3 wealth rewards just for participating, and an additional 4 wealth points if you answer correctly~~~ Short answer question: What parts are mainly checked chemically during boiler overhauls? The main components inspected include the steam drum, water wall lower header, superheater, reheater, economizer, and deaerator
Reply #22016-04-28
The main inspections are carried out on the steam drum, water wall tubes, water wall lower header, superheater, reheater, economizer, and deaerator.
Reply #32016-04-28
The main components inspected are the steam drum, water wall tubes, water wall lower header, superheater, reheater, economizer, and deaerator
Reply #42016-04-28
The main inspections are carried out on the steam drum, water wall lower header, superheater, reheater, economizer, and deaerator.
Reply #52016-04-28
Superheater, reheater, economizer, and deaerator.
Reply #62016-04-28
Steam drum (inspect internal components), pipes, water wall and downcomers, feed water pump
Reply #72016-04-28
The main inspections are carried out on the steam drum, water wall tubes, water wall lower header, superheater, reheater, economizer, and deaerator.
Reply #82016-04-28
Answer: The main components to be inspected are the steam drum, water wall tubes, water wall lower header, superheater, reheater, economizer, and deaerator
Reply #92016-04-28
Steam drum, water wall tubes, water wall lower header, superheater, reheater, economizer, and deaerator
Reply #102016-04-28
1. Steam drum; 2. Water wall ; 3. Lower water wall header ; 4. Economizer ; 5. Superheater.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.