【First-Class Constructor Project Management Practice Questions】036 Construction Party’s Project Management Objectives and Tasks

2016-06-20View Original

Thread Content

Which of the following statements about the project management objectives and tasks of the contractor is correct? (  ) (2015 Exam Question) A. The project management carried out by the contractor serves only the interests of the contractor itself. B. Project management by the contractor does not involve the preparation phase prior to commencement of work. C. The cost targets set by the contractor are determined by the construction company based on its own production and operational conditions. D. The contractor is not responsible for the goals and tasks assigned to subcontractors appointed by the owner. 【Correct Answer】C 【Answer Explanation】This question examines the goals and tasks of project management conducted by the contractor. The project management services provided by the contractor should serve not only the interests of the contractor itself but also the overall interests of the project; therefore, option A is incorrect ; The project management work carried out by the contractor mainly takes place during the construction phase; it also involves the preparation stage prior to commissioning and the warranty period, so option B is incorrect ; The cost targets of the general construction contractor or the general construction management contractor are determined by the construction company based on its own production and operational conditions, while the cost targets of the subcontractors are set internally by the construction company itself; therefore, option C is correct ; The general construction contractor or the general construction management contractor shall be responsible for the time and quality targets specified in the contract; option D is incorrect. See page P15 of the textbook.
Reply #22016-06-20
C. The construction party’s cost target is determined by the construction enterprise itself based on its production and operational conditions
Reply #32016-06-20
 C. The construction party’s cost target is determined by the construction enterprise itself based on its production and operational conditions
Reply #42016-08-11
D. The contractor is not responsible for the objectives and tasks assigned to the subcontractors designated by the owner

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.