To those designers who only work on paper: Please stop teasing us workers like this (2)

2016-07-29View Original

Thread Content

[Serial Article] To those designers who only talk the talk: Please stop teasing us workers like this (2). More examples of such irresponsible and foolish designs will be posted going forward. If you’re interested in this content, please follow us as indicated in the image above or share this article! http://bbs.hg707.com/data/attachment/forum/201606/19/091722zl7vv37z5uee5nuv.png During construction, the civil engineering team said that the drawings did not include any provisions for drainage ditches; I found this hard to believe. Construction photos are attached. After the hardened surface was completed, it was discovered that there were no ditches for pumping out water, and I was shocked at that moment. http://bbs.hg707.com/data/attachment/forum/201606/19/091728mnrptia20ddn02aa.png After realizing this, we used a pneumatic hammer to create openings in those areas; it took a long time, but the quality of the surface remained acceptable. http://bbs.hg707.com/data/attachment/forum/201606/19/091734khogvhv5vzv8tvv1.png Corrective measures: After the problem was identified, part of the bottom surface was broken open using a pneumatic hammer, and new drainage channels were created. It’s difficult to install the flanges at the larger and smaller ends without using connectors. http://bbs.hg707.com/data/attachment/forum/201606/19/091738ihiqh6r62hog8rro.png http://bbs.hg707.com/data/attachment/forum/201606/19/091742kgcvpdebcbifs767.png The inlet and outlet of the pump are equipped with larger and smaller ends, which are directly welded to the flanges; this is not standard practice. Moreover, due to these larger and smaller ends, it’s difficult for bolts on the smaller end to pass through, making it inconvenient to disassemble or tighten components. A straight section of pipe should be added in front of the larger and smaller ends. The process pipelines should be installed above the manhole covers. http://bbs.hg707.com/data/attachment/forum/201606/19/091745ett2e0t7oo0q2t00.png The design for water supply and drainage should be handled separately; the piping design did not take into account the requirements of the water supply and drainage system, resulting in the pipes passing directly through the manhole covers, which makes it impossible to open them. Conclusion for today: Don’t become a joke in others’ eyes.
Reply #22016-07-29
I was also shocked by the digging of drainage ditches – why dig them? The water pumped out by the seal is directly discharged into the ditch – why not reuse it? Even if it needs to be discarded, pipes can simply be connected to the ditch; what’s the point of digging such a large ditch?
Reply #32016-07-29
It would be more appropriate for the original poster to put this in the safety section, as it can serve as an image of a potential hazard...

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.