Daily Question 2015.7.25 (EIA Discussion): 3 Wealth points for replies, plus 5 Wealth points for correct answers (multiple-choice question)

2015-07-25View Original

Thread Content

51. Three months after the trial production of a petrochemical project, it entrusts a qualified entity to carry out the environmental protection completion inspection, which requires on-site inspections (). A. Feasibility study report B. Environmental monitoring instruments and equipment C. Online monitoring equipment for main drainage outlets D. Enterprise environmental management system Correct answer: BCD Explanation: See the Technical Specifications for Environmental Protection Acceptance of Construction Projects
Reply #22015-07-25
B. Environmental monitoring instruments and equipment C. Online monitoring equipment for main drainage outlets D. Enterprise environmental management systems
Reply #32015-07-25
I think the answer should be that all three, bcd, are needed
Reply #42015-07-26
Three months after the trial production of a petrochemical project, it commissioned a qualified entity to carry out the environmental protection completion inspection, which requires on-site inspections (B, C, D). Answer: B. Environmental monitoring instruments and equipment C. Online monitoring equipment for main drainage outlets D. Enterprise environmental management systems
Reply #52015-07-26
B. Environmental monitoring instruments and equipment: D:D
Reply #62015-07-26
51. Three months after the trial production of a petrochemical project, it commissioned a qualified entity to carry out the environmental protection completion inspection, which requires on-site inspections (bcd). A. Feasibility study report B. Environmental monitoring instruments and equipment C. Online monitoring equipment for main drainage outlets D. Enterprise environmental management system
Reply #72015-07-26
The answer is: A B C D
Reply #82015-07-26
Three months after the trial production of a petrochemical project, it commissioned a qualified entity to carry out the environmental protection acceptance inspection upon completion, which requires on-site inspections (). B. Environmental monitoring instruments and equipment C. Online monitoring equipment for main drainage outlets D. Enterprise environmental management systems
Reply #92015-07-26
B. Environmental monitoring instruments and equipment C. Online monitoring equipment for main drainage outlets D. Enterprise environmental management systems

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.