Participation reward: 2 Wealth. Reward for correct answer: 9 Wealth. Multiple-choice question: During the construction of a research and development center, the formwork structure collapsed while concrete was being poured in the lobby, resulting in 12 deaths and 16 injuries. Upon investigation, it was found that the accident was mainly caused by the technical supervisors on site being sick and on leave; in order to avoid delays in the construction progress, the project supervisor ordered the workers to carry out their work without providing any technical instructions. As a result, the quality of this project should be rated as ( ). A. Accidents caused by management reasons B. Accidents caused by technical reasons C. Extraordinarily serious accidents D. Accidents due to failure in supervision E. Serious quality accidents
A. Accidents caused by management reasons B. Accidents caused by technical reasons C. Extraordinarily serious accidents D. Accidents resulting from leadership failures E. Serious quality accidents
A. Accidents caused by management reasons B. Accidents caused by technical reasons C. Extraordinarily serious accidents D. Accidents resulting from leadership failures E. Serious quality accidents
During the construction of a research and development center, the formwork structure collapsed while concrete was being poured in the lobby, resulting in 12 deaths and 16 injuries. Upon investigation, the accident was mainly caused by the on-site technical managers being sick and on leave; in order to avoid delays in the construction progress, the project supervisor ordered the workers to carry out the work on their own without providing any technical instructions. The quality of this project should be classified as (E. Serious quality accident).
During the construction of a research and development center, the formwork structure collapsed while concrete was being poured in the lobby, resulting in 12 deaths and 16 injuries. Upon investigation, the accident was mainly caused by the on-site technical managers being sick and on leave; in order to avoid delays in the construction progress, the project supervisor ordered the workers to carry out the work on their own without providing any technical instructions. The quality of this project should be rated as (AE). A. Accidents caused by management reasons B. Accidents caused by technical reasons C. Extraordinarily serious accidents D. Accidents resulting from failure to provide proper guidance E. Serious quality accidents